  • This project consisted of works within various areas of the plant to achieve the working space required to facilitate the installation of a new Wet Line manufacturing process.

  • The project entailed initial co-ordination and relocation of various sectors and operations within the plant to allow the project to progress fully and free up required work areas.

  • Phase 1 comprised the construction of new mezzanine floor offices within the existing plant and the construction of an extension to the chemical handling room.

  • Phase 2 involved relocation of existing service rooms and toilet facilities to accommodate the construction of new production area.

Boston Scientific Wetline 3

  • Boston Scientific Ireland Ltd
  • Boston Scientific Wetline 3
  • PM Group
  • €2,400,000.00
Download the latest New Build MJ Conroy Brochure

This project consisted of works within various areas of the plant to achieve the working space required to facilitate the installation of a new Wet Line manufacturing process.
The project entailed initial co-ordination and relocation of various sectors and operations within the plant to allow the project to progress fully and free-up required work areas.

<!--[endif]-->

The work was completed over two phases:

* Phase 1 comprised the construction of new mezzanine floor offices within the existing plant and the construction of an extension to the chemical handling room.
* Phase 2 involved the relocation of existing service rooms and toilet facilities to accommodate the construction of a new production area.
The project was completed over a seven-month programme period.

 

 